(KLZA)--Weather permitting, work is scheduled to begin Monday, March 28th on Nebraska Highway 2, from Lincoln to Syracuse.
Western Engineering Company, Inc. of North Platte, Nebraska, has the $4,931,836 contract for milling and asphalt resurfacing of both inside and outside shoulders for westbound and eastbound lanes. Work will also include milling and resurfacing of ramps on Nebraska-43 and Nebraska-50 interchanges.
During construction, the Nebraska Department of Roads says traffic will be maintained in one lane. The project is anticipated to be completed by September.