(KNZA)-Doniphan County officials took a closer look at two courthouse projects during their meeting Monday.
First, members of the Freedom Rock Foundation outlined plans to install a 23-thousand-pound granite “Freedom Rock” in the courthouse courtyard to honor local veterans. Painting of the monument is scheduled for late September of 2026. Commissioners toured possible locations but held off on a final decision until more details on installation are available.
The Commission also revisited the courthouse steps and handrails project, which has faced delays since it was approved in 2024. New handrails were recently installed, but one section did not match the existing design. After discussion, the contractor agreed to redo the railing at no additional cost to the county.
Officials also raised concerns about the snow-melting system in the courthouse steps, which has not worked for the past two winters. The contractor says repairs are now complete, the system is fully operational, and the warranty has been extended through 2032. Documentation confirming proper materials were used will also be provided.