The cost will be $9.93 per ton which will amount to a total of nearly $74,500 in hauling fees.
Commissioners also met with representatives of Van Dorn Valley Constructions to review the Dawson Northwest project completion and final payment.
The County determined that $11,843 has been incurred in liquidated damages because the work was not completed on schedule.
The work began May 27, 2026 and had a contracted completion date of June 19, 2026.
The company representatives presented information on the facts that hindered their ability to complete the project on time, including excessive rainfall and a sub-contractor for concrete work, leaving the project and it becoming a struggle to find another contractor to complete the cement work.
The Board voted unanimously to not to pay the contract amount of $40,721, withholding the $11,843 in liquidated damages.