(KAIR)--A deteriorating walkway at Atchison's water treatment plant will be replaced following action taken during Monday's meeting of the Atchison City Commission.
Commissioners approved a $42,900 contract with L & L Construction to replace the elevated walkway connecting two buildings at the facility.
Public Works and Utilities Director Clinton McNemee told commissioners the existing concrete walkway has deteriorated, with pieces of concrete falling from the structure and the anchors securing the handrails becoming exposed.
McNemee said the condition of the handrails created safety concerns and increased the urgency of replacing the walkway.
The project calls for removing the concrete deck and replacing it with metal grating. The existing steel support beams will be cleaned and recoated, while the current handrails will be reused.
The replacement design was developed by the city's engineering consultant.
McNemee said the project was originally estimated to cost $150,000, but the city received a single bid from L & L Construction for $42,900, less than one-third of the original estimate.
The city advertised the project and invited local contractors to submit proposals.
Commissioners approved an overall project budget of $50,000, allowing for potential additional expenses or unforeseen conditions during construction.
McNemee said work could begin once the contractor is available, although obtaining the metal grating could affect the timeline. He indicated mobilization could take up to a couple of months.
During construction, employees will be able to use alternative routes between the buildings.
The walkway replacement is included in the city's 2026 Capital Improvement Program.