(KAIR)--Years of work to separate Atchison's stormwater and sanitary sewer systems could soon reach an important milestone, with an upcoming project potentially eliminating one of the city's combined sewer overflow points for the first time.
During the November 16 meeting of the Atchison City Commission, City Manager Mark Westhoff provided an update on several ongoing sewer infrastructure projects, including the 15th Street sewer separation project being handled by the U.S. Army Corps of Engineers.
Westhoff said bids for the project were expected to be opened the following week.
The city has spent approximately two decades working to separate stormwater from sanitary sewage, particularly in older neighborhoods where both are carried through the same system.
During heavy rainfall, the combined system can become overwhelmed, resulting in overflows that discharge a mixture of stormwater and untreated sewage into White Clay Creek and the Missouri River.
Westhoff explained that the combined system also creates additional costs for the city's wastewater treatment operations because rainwater is routed to the treatment plant along with sewage.
The separation projects are part of the city's efforts to comply with state environmental requirements and reduce the frequency of combined sewer overflows.
Westhoff said the city has made progress through a series of projects over the years, generally working from west to east as funding becomes available.
The 15th Street project represents a potentially significant step because it could allow the city to completely close one of its existing combined sewer overflow points.
Previous improvements have helped reduce the number and frequency of overflows, but Westhoff said the 15th Street project could be the first to eliminate an overflow point entirely.
The city is also nearing completion of its South Headworks improvement project, which Westhoff said has been a long time coming.
The project carries a total cost of approximately $2.4 million, including about $700,000 in grant funding. The city is covering the remaining costs, which can also count toward required local matching funds for current and future federally supported sewer improvements.
Westhoff indicated during the November 16 meeting that the South Headworks project could be completed within the next several weeks.
Additional work is continuing at the wastewater treatment plant, where contractors are reconstructing the facility's bio tower.
Crews have removed the collapsed internal material, applied protective coatings to the interior walls and continued work on piping. Replacement material is expected to be installed in January.
Meanwhile, Atchison is pursuing another major partnership with the U.S. Army Corps of Engineers through its Section 219 program.
A proposed project partnership agreement totals approximately $13.33 million, with $10 million in federal funding and a local share of about $3.33 million.
The city's proposed contribution would come from its water and sewer funds.
According to the letter of intent included with the November 16 City Commission agenda, the proposed local contribution does not legally or financially obligate the city at this stage.
Westhoff noted that separating the city's combined sewer system remains a long-term undertaking, with the costs extending well beyond individual projects.
The city continues to pursue federal assistance and other funding opportunities as it works to meet environmental requirements and improve its wastewater infrastructure.