(KAIR)--A bridge replacement project is underway in Jefferson County, with the Commission, this week, provided with an update regarding the work, including the timeline for the affected roadway closure.
The update, according to the unofficial Jefferson County Commission meeting minutes from Monday, was provided by County Public Works Director, Ben Domann.
Domann, the minutes say, told the County Commissioners the work on the McCall Drive bridge began April 21, with the bridge now demolished.
Domann informed the Commission that the bridge will remain out of service for around 3-months.
Domann, citing the contractor on the bridge project, told the Commissioners the new bridge will be double that of the former bridge, spanning 120 feet.
© Many Signals Communications
MOST VIEWED STORIES
Holton schools mourn student death
Info sought on missing Sabetha teen
Missing Atchison couple draws renewed interest
Fleeing, drugs, hold Atchison man
Atchison's USD 409 names new Superintendent
ATCH CO SO seeks tips regarding stolen motorcycle
Jackson Heights names new MS/HS Principal
Atchison foundry renamed in acquisition
Tecumseh Prison inmates arrested for 2023 assaults
NioCorp to begin 12-week drilling program
Olathe woman arrested in Jackson Co on drug charges
Hiawatha City Commission approves fireworks on trial basis
Longtime Sabetha Fire Chief to retire
Two new members appointed to Brown Co Planning Commission
Dean, assistant, secured for proposed BC med school
Falls City Council hears updated on electric department
Early morning power outage planned for Falls City
Flags to fly at half-staff in honor of fallen firefighters
LATEST STORIES
Dean, assistant, secured for proposed BC med school
Richardson Co board conducts grievance hearing
Update to Nebraska State Park burn bans
Holt Co, Mo bridge project delayed
Auburn, Neb to celebrate 143rd birthday
Flags to fly at half-staff in honor of fallen firefighters
Auburn School Board approves administrator salaries
Tecumseh Prison inmates arrested for 2023 assaults