(KNZA)--The Nemaha Central USD 115 Board of Education in a special meeting Wednesday evening approved the next step of construction on the $24.2 million bond project approved by voters last November.
The board approved bid package #3 with a total guaranteed maximum price of $12,064,812. It's for work that finishes the new classroom additions and is the largest bid package to date.
The total contract sum to date stands at $14.7 million.
Still left is bid package #4 for work to remodel the CTE building and upgrades to the high school parking lot.
A ground breaking ceremony was held in June for the bond project
Bern-based AHRS Construction is serving as construction manager on the project.
© Many Signals Communications
MOST VIEWED STORIES
Effingham woman killed Friday in Atchison wreck
One hospitalized, one jailed, after Atchison attack
Atchison man involved in fatal NW MO crash
Rural Horton man arrested on multiple drug charges
Street lights to be discussed at Monday city meeting
Services set for Effingham woman killed in crash
Meteorologist Spencer: Geometric Watch means electronic disruptions
Two file to challenge local legislator
USD 430 Board accepts resignations, approves new hires
U.S. 36 work in Doniphan Co to impact motorists
Truck fire at CGB facility in Falls City
Flags to fly half staff Wednesday across KS
Results from SE Nebraska contested Primary Elections
BC's Pate remembered by students, college family
Fatal Atchison apt fire investigation continues
Update: Date set for signals switch at Hiawatha intersection
Three former Atchison Co employees arrested on felonies
LATEST STORIES
Three former Atchison Co employees arrested on felonies
Barricaded fugitive arrested in Jackson County
Wed signing means full funding for KS education
MHMA Mock Trial Team sees natl success
Fatal Atchison apt fire investigation continues
Update: Date set for signals switch at Hiawatha intersection
Results from SE Nebraska contested Primary Elections
U.S. 36 work in Doniphan Co to impact motorists