K-99 resurfacing work planned in Marshall Co
06/30/2025

(KMZA)--The Kansas Department of Transportation will begin resurfacing work on K-99 in Marshall County the week of Monday, June 30, conditions permitting.

The mill and overlay project spans about 15 miles, starting at the Kansas/Nebraska state line and progressing south to the U.S. 36 junction.

Traffic will be restricted to one lane and directed by a pilot car and flaggers where crews are actively working. Drivers should plan for delays of up to 15 minutes. A 10-foot width restriction will also be in effect.

Work will occur during daylight hours Monday through Friday, and Saturdays as needed.

Hall Brothers Inc., of Marysville, is the prime contractor on the $3.3 million project, which is expected to be complete by the end of August.