Weather permitting, work is scheduled to begin the week of May 29 at the junction of N-8 and N-99, Reference Post 98.74 to 103.38, south of Burchard, according to the Nebraska Department of Roads.
Constructors, Inc., of Lincoln, has the $1,637.403 contract to extend three box culverts, install new guardrail, do a lime slurry stabilization and three-inch bituminous overlay. Traffic on the 4.64-mile project will be controlled by one-lane work zones and flaggers where necessary.
Completion of the project is anticipated in September.
The Department of Roads’ project manager is Bill Jasa of Tecumseh. Motorists are reminded to drive cautiously through highway construction zones.
© Many Signals Communications
MOST VIEWED STORIES
Couple arrested on drug charges after traffic stop
Hartman sentencing in the hands of judge
Competency evaluation sought for man charged in murder of Seneca priest
Traffic stop sends driver to DHS custody
New Sabetha city administrator hired
Update: Atchison boil water advisory lifted
Property damage in DUI leaves Iowa man charged
Multiple crews battle Hoyt area fire
Topeka man arrested after Jackson Co pursuit and manhunt
Hearing set on proposed Nemaha Co Land Development Code
Grand Opening held for Underground Railroad exhibit in Falls City
Woman arrested in Jackson Co on meth charge
Probation for LV woman convicted in child death
KASB to assist USD 415 in search for new Superintendent
Sheriff's Office releases 3rd quarter 2025 patrol statistics
KDOT approves bids for area projects
Pay increase approved for Hiawatha city employees
New Nemaha Co Treasurer sworn in
LATEST STORIES
Four injured in Friday Jackson Co crash
Seneca City Council approves hiring of new police officer
Falls City Utilities planned power outage
Multiple crews battle Hoyt area fire
Doniphan Co to seek grant again for ADA project
Advance voting underway in Nemaha Co
KASB to assist USD 415 in search for new Superintendent
Doniphan Co RWD no longer under boil water advisory
RELATED STORIES
Highway 73 Work Planned at Verdon
Highway 105 Work Scheduled to Begin
Highway Work To Begin South of Falls City
Highway 73 Work Begins North of Falls City
Highway 75 Work North of Auburn to Begin April 2nd
Highway Work to Begin in Humboldt Area April 30th
Highway 136 Work on Schedule Through Auburn